Home -Project Cases - Prefabricated Steel Structure Photovoltaic Solar Panel Workshop with 10 Tons Overhead Crane In Chile

Prefabricated Steel Structure Photovoltaic Solar Panel Workshop with 10 Tons Overhead Crane In Chile

A: Parameter table about Prefab Steel Structure Photovoltaic Solar Panel Workshop Shed

Building Size:30*15*7.5m workshop with 15×12 prefab office building

Steel beam&column Material :Q345B

Roof covering:Single steel sheet

Wall covering:single steel sheet

Door:Two big sliding door width 6.5m height 4.5m and two small access door

There are no windows,the client will install a small number of solar panels for indoor lighting in future.

B: Professional designers provide design drawings to you at first time,this is drawing of Steel Structure Solar Panel Workshop Shed In Chile

1.png

C: The advantages of steel structure workshop

The steel structure workshop has the advantage of wide span, high strength, light weight, low cost, temperature protection, save energy,beautiful appearance, short construction time, good effect of insulation, long using life, space-efficient, good seismic performance, flexible layout,etc.

D: Special requirements of Steel Structure Photovoltaic Solar Panel workshop Project

1. Our client choose design with 10 tons overhead crane for lifting heavy goods for his workshop area.

2. Maximum seismic level for the Chile Special geographical

E: Chile Clients visiting of prefabricated Steel Structure Photovoltaic Solar Panel workshop Project

We shown our clients the entire production process of our workshop introduced the the production equipment and the details of each production process & related high quality production standards..On our expanding workshop construction site, clients inquiry some installation questions, We answered one by one, and introduced the entire installation process and some installation precautions of prefabricated steel structure workshop.Our client is very satisfied with us.

2.png

F: Package & Delivery

We will package goods so it’s easy to put into the containers. Under normal circumstances, the cycle time about from order to delivery, steel structure building is in 30 working days .we can transport goods to the Tianjin port then transportation by sea.all cargo be sterilized during loading.

6.jpg

G: Installation process of metal workshop building

We provide complete construction drawings and installation instructions. And there are staff to guide the installation throughout the process.In addition, our design simplifies the installation steps, and only bolts are required on site. Even for customers who are first time build, the installation can be done quickly and easily.

7.jpg

8.jpg

Our Client was very satisfied with our steel structure components,not only the competitive price ,but our high quality and excellent after-sale service.

He introduce several Chile projects to us. Thanks for client’s trust and support.


Online Service×